Building Timelines

Stage 1 (Completed 4 July 2011)

  • January 2009 – July 2009 – Schematic design
  • February 2009 – Forward Brianese Architects engaged.
  • October 2009 – Design development completed.
  • 5 October 2009 – Parliamentary Standing Committee for public works approval.
  • November 2009 – January 2010 – Early works tender period.
  • January 2010 – Early building works tender approved and contractor (Hazell Bros) selected.
  • 10 February 2010 – Early building works commenced.
  • 3 March 2010 – Main building works tender closed.
  • Mid March 2010 – Early building works completed.
  • May 2010 – Main builder appointed. (VOS Construction)
  • June 2010 – Main building works commence.
  • June 2010 – 4 July 2011 - Stage 1 construction

Stage 2 (Scheduled for completion April 2012) 

  • July 2011 - April 2012 - Stage 2 constructionLooking over old CCHC site towards Bayfield Street